The following activities are part of a project to be scheduled using CPM:
Activity | Predecessors | Duration |
---|---|---|
A | 6 | |
B | A | 3 |
C | A | 7 |
D | C | 2 |
E | B,D | 4 |
F | D | 3 |
G | E,F | 7 |
a) Draw the network
b) What is the critical path?
c) How many weeks will it take to complete the project?
d) How much slack does the activity B have?