The following activities are part of a project to be scheduled using CPM:
Activity | Immediate Predecessor | Time (weeks) |
---|---|---|
A | - | 8 |
B | A | 3 |
C | A | 7 |
D | C | 3 |
E | B,D | 4 |
F | D | 3 |
G | E,F | 6 |
a. What is the critical path?
b. How many week will it take to complete the project?
c. How much slack does activity B have?